Several technicians at once for rollouts in the data center, over days or weeks. At night and across Europe by arrangement.
Goods receipt, installation, cabling and checks in one go, as with rack & stack.
Installation of GPU servers with NVIDIA H100 and H200.
Replacing parts across many servers, with serial numbers per device.
Clarify scope, plans, time windows and access.
Define team and order, check material.
A daily status with completed and open items.
Final report with all devices and serial numbers.
No. We work in the data center: servers, racks, GPU systems and their cabling.
Ideally 1 to 2 weeks. For shorter deadlines, please ask directly.
Yes, so far including Paris, Marseille, Brussels and Stockholm.
Ali Tut, from quote to report. During the rollout you get a status every day.
Send us the site, the task and the time frame. You get an answer with our availability. We answer in English or German.